This is the second weekly report sent from Siemens – Brian Rancourt

Hi All,

After the second week solid progress continues  (see below pictures) and attached updated schedule.

  • New equipment curbs have been located and placed on the roof.
  • Earthwork and concrete for the new foundation and walls has started.
  • Next week the building insulation crew will arrive.
  • Lacewood and NPI are on site full time.

Please contact me with any questions.

Thank you,

Brian